Memo
To: Dr. Carla Kungl
From: Ship Room Raters
Subject: Work
Plan
Date: October 2, 2009
Purpose
The
purpose of this memo is to provide you with our work plan pertaining to the
development of a website for Ship Room Raters. The website is primarily
intended for students at Shippensburg University seeking off-campus housing. We
will discuss the topic we have chosen for the website, our time schedule
represented by a Gantt chart, a list of our group’s policies, and a job
description of our project leader.
Our Topic
The
project we decided to undertake for our website is to provide housing resources
to the freshman class of Shippensburg University for after their first year
when they are hunting for new apartments. Our reasoning for this is because
when we were freshman, we thought it would have been useful to have a website
that offers student reviews about housing units around campus. In
order to accomplish our goal of providing these resources, we conducted
informal research in order to determine the most popular off-campus housing
units.
Later we are going to survey students who live in these units and use
that information to develop our website. Based on questions ranging from
cleanliness, location, security, and others, we will provide a thorough
resource for all potential tenants.
We anticipate that the website will have an
overview map of the town with the locations of major apartments and townhouses
sectioned off. The website will focus on three specific student housing
communities, which will be represented in our individual pages. This will allow
those who visit the site to compare and contrast them at the click of a mouse.
Project
Activities
To
best illustrate our planned project activities, we will include within this
document a Gantt Chart. (Fig. A) We also have attached our full work schedule. (Table 1)
Figure
A. Gantt Chart
Task
|
Date of Tasks
|
||||||||||||||||||
Work Schedule
|
|||||||||||||||||||
Create Logo/Letterhead
|
|||||||||||||||||||
Draft Work Plan
|
|||||||||||||||||||
Proofread Work Plan
|
|||||||||||||||||||
Submit Work Plan
|
|||||||||||||||||||
Gantt Chart
|
|||||||||||||||||||
Secondary Research
|
|||||||||||||||||||
Primary Research
|
|||||||||||||||||||
Draft Proposal
|
|||||||||||||||||||
Proof Web Proposal
|
|||||||||||||||||||
Submit Web Proposal
|
|||||||||||||||||||
Create Survey
|
|||||||||||||||||||
Distribute Survey
|
|||||||||||||||||||
Home page design
|
|||||||||||||||||||
Draft Indiv. Websites
|
|||||||||||||||||||
Usability checks
|
|||||||||||||||||||
Prepare for Presentation
|
|||||||||||||||||||
Presentation
|
|||||||||||||||||||
Weeks
|
1
|
2
|
3
|
4
|
1
|
2
|
3
|
4
|
1
|
2
|
3
|
4
|
1
|
2
|
3
|
4
|
|||
September
|
October
|
November
|
December
|
||||||||||||||||
(The
lightest shade of grey represents beginning the task. As progress is made, a darker
shade is used. Black expresses completion of the task.)
Group Policies
Below
is the list of our group policies:
·
A
team member must provide ample notification to the group leader if they are to
miss a meeting.
·
The
work must be completed on the date it is due.
·
If
deviant behavior continues to happen from a group member, the professor will be
notified to allow for further discipline.
·
If
a general consensus cannot be met within the group, then it will be settled by
flipping a coin.
·
Before
work is submitted, the group as a whole must proof-read it.
·
If
anyone has a problem with another group member, the group leader must be
notified first.
Project Leader: Mike Edwards
The
job of the group leader is to keep the group on task, as well as lead meetings,
coordinate communication amongst the group members, and be the liaison between
the group and the professor. The group leader for our group will not assign any
work to group members. The group will handle all assignments as a team.
Table
1. Work Schedule
Name of Project: Ship
Room Raters (Proposal for Website)
Principal Reader: Dr.
Carla Kungl
Group Members: Mike
Edwards, Beth Weyer, Robert (Bobby) Wood
Milestones
|
Responsible
Member
|
Hours
|
Status
|
Completion
/ Due Date
|
||||
*PRESENTATION
|
All
|
15 min.
|
Fri. December 11
|
|||||
Prepare for
presentation
|
All
|
3 hours
|
Thr. December 10
|
|||||
*MEMO: USABILITY
SUGGESTIONS
|
Individual
task
|
.5 hours
|
Mon. December 7
|
|||||
*USABILITY STUDIES
|
All
|
1 hour
|
Wed. December 2
|
|||||
*DRAFT INDIVIDUAL
WEBSITES
|
Individual
task
|
2 hours
|
In progress
|
Mon. November 30
|
||||
*SUBMIT
HOMEPAGE DESIGN
|
Bobby
|
Complete
|
Fri. November 6
|
|||||
Homepage Design
|
Bobby
|
3 hours
|
Complete
|
Mon. October 26
|
||||
Compile Research
|
Mike
|
1.5 hour
|
In progress
|
Thr. November 5
|
||||
Distribute Survey
|
All
|
1 hour
|
Complete
|
Thr. Ocotober 29
|
||||
Revise Survey
|
Beth
& Bobby
|
.5 hour
|
In progress
|
Mon. November 2
|
||||
Create Survey
|
Bobby
|
.5 hour
|
Complete
|
Mon. Oct 26
|
||||
Primary Research
|
All
|
3 hours
|
Complete
|
Wed.
November 4
|
||||
Secondary Research
|
All
|
1 hour
|
Complete
|
Wed. November 4
|
||||
*SUBMIT WEB PROPOSAL
|
Mike
|
Complete
|
Wed. October 28
|
|||||
Proofread Proposal
& make corrections
|
All
|
3.5 hours
|
Complete
|
Fri. October 23
|
||||
Draft Proposal
Sections
|
All
assigned separate sections
|
2 hours
|
Complete
|
Wed. October 21
|
||||
Updating Gantt Chart Initial
Creation of Gantt Chart
|
Beth Bobby
|
1 hour 1hour
|
Ongoing
|
Submit w/ each
assignment
|
||||
*SUBMIT WORK PLAN
|
Mike
|
Complete
|
Fri. October 2
|
|||||
Proofread Work Plan
|
All
|
30 min.
|
Complete
|
Mon. September 28
|
||||
Draft Work Plan
|
Mike
|
1 hour
|
Complete
|
Wed. September 23
|
||||
Logo, Letterhead,
Bus. Name
|
Beth
& Bobby submit ideas
|
1.5 hours
|
Complete
|
Mon. September 28
|
||||
Work Schedule
|
Beth
|
1 hour
|
Ongoing
|
Submit w/ each
assignment
|
||||
Progress Reports
|
Responsible Member
|
Status
|
Date
|
|||||
Status Report
|
Bobby
& Beth
|
Complete
|
Wed. November 18
|
|||||
Meetings
|
Agenda
|
Location
|
Hours
|
Date
|
Time
|
|||
Meeting 4
|
Status
Report
|
Library
|
2hours
|
Mon. Nov. 16
|
9:00 pm
|
|||
Meeting 3
|
Edit
Web Proposal
|
Dr.
Kungl’s Office
|
20 min
|
Mon. Sept. 26
|
10:00 am
|
|||
Meeting 2
|
Finalize
Work Plan, letterhead, and Gant Chart
|
Library
|
1
|
Wed. Sept. 30
|
5:00 pm
|
|||
Meeting 1
|
Draft:
Work Plan, Gant Chart, Work-Schedule, Creative
|
Library
|
1.5
|
Wed. Sept. 23
|
5:00 pm
|
|||
Notes
Project Leader: Mike Edwards
Webmaster: Bobby Wood
Creative Design: Beth Weyer
|
||||||||